The table below sets out appropriate detailing at eaves where:
- Insulation (rigid board type) following line of rafter with insulation level with top of rafter or on top of rafter.
50mm x 50mm counterbattens installed on top of underlay.
- A trapeziodal composite insulated warm roof system is to be installed under the roof tiles
For warm roof constructions with insulation inset into rafters with a 50mm airgap between top of insulation and top of rafter, click here
|
Insulation (rigid board type) following line of rafter with insulation level with top of rafter or on top of rafter.
50mm x 50mm counterbattens installed on
top of underlay.
|
Trapeziodal composite insulated warm roof system, installed under the roof tiles
|
| Eaves ventilation system |
Provide Decra Eaves Mesh with free airflow of 25,000mm² per linear metre. |
Provide mesh with free airflow of 25,000mm² per linear metre. |
| Setting out point for fascia board |
Level with top edge of rafter or top edge of insulation board. (If installation boards are installed). |
|
| Install |
N/A |
N/A |
| Install |
Install Decra 700 High Performance Breather membrane on top of rafters and under counterbattens. |
N/A |
| Install eaves batten to rear of fascia board |
|
Install eaves batten the same size as tile batten installed behind fascia board. |
| Install Decra Eaves Guard |
Decra Warm Roof Eaves Guard installed under Decra 700 High Performance Breather membrane. Use of Decra Eaves Mesh & Decra Eaves Closure Flashing recommended. |
N/A, Use of mesh & Decra Eaves Closure Flashing recommended. |