Decra Plus Verge/Gables Design

 

Decra Plus Tile - Verge/Gable design  using D type Box Barge Cap - Detail from drawing DPSE052
 

Installation Guidance - Decra Plus Tile D type Box Barge Cap

Setting Out Gables
Fix the barge boards in a position where they are level with the tops of the tile battens.
Underlay should turn up against the edge of bargeboard by 38mm.

On top of the tile battens nail additional gable runner battens up the slope of the roof and along the vertical face of the bargeboard. These battens should be set 85mm from the outer top edge of the bargeboard (see drawing to right).
 

 

 

 

 

  

 

 

Gables
The gable detail is finished using a Decra D Box Barge Cap.  The D Box Barge Cap is similar to the D Ridge in appearance but the angle is much steeper (see below).

 

 

 

 

Decra tiles to be cut and bent forming an upstand against a gable runner batten.

Before installing the first D Box Barge Cap it is necessary to trim and fold the ends to form a blocked end at the eaves.  Mark out a line 40mm from the bottom edge of D Box Barge Cap. Cut away areas shaded black on image below. Fold vertical flap 90° in on itself, fold horizontal flap down by 90°.

 

 

 

 

The D Box Barge Caps have a slight taper in their design. Place the wider end of the D Box Barge Cap over the narrower top end of the D Box Barge Cap beneath creating an 80mm overlap.

 

   


Nail D Box Barge Cap into position using 4 nails skew fixed down the inner face of the D Box Barge Cap into the upstand of the tile and 4 horizontally (see images below. Care should be taken to ensure D Box Barge Cap are correctly lapped.

 

 

 

 

 

Contact

Let Decra offer you expert advice and information at every stage of your project.

For technical advice and assistance.

01293 545058

Or for local advice
technical advice and support