1. Install 50 x 38mm vertical battens, fixed to tile battens at both faces of the corner.
2. Bend tiles to form 25–38mm upstand against vertical battens.
3. Position Ridge/Barge Cap over vertical battens and tile upstand.
4. Fix with one Decra Nail each side of the Ridge/Barge Cap near the end lap.
Let Decra offer you expert advice and information at every stage of your project.For technical advice and assistance.01293 545058Or for local advice technical advice and support
Useful downloads
CAD Library Decra's CAD & drawing library Installation GuidesInstallation Guides & Decra Literature Decra LiteratureBrochures and certificationVideo (System Performence)Video demonstrations showing the Decra roof systems outstanding performanceVideo (Detailing Guide)Video Installation guide, demonstrating how Decra roofs can be correctly detailed